Installing CITA Smart 7 - Prerequisite and Preparing
Installing
Warning Electric Shock
INSTALLATION OF ANY ELECTRICAL DEVICE SHOULD BE CARRIED OUT BY A SUITABLY QUALIFIED AND COMPETENT PERSON.
A qualified person has the skills and knowledge related to the construction, installation, & operation of electrical devices and who has received safety training to recognize and avoid the hazards involved.
Keep in mind
Before installing the CITA Smart 7, make sure that the power line you’re using is switched off on your service panel.
Make sure that the power line to CITA Smart 7 is installed on a dedicated circuit breaker (MCB) on your service panel. The installation must incorporate an adequate residual current device (RCD).
The MCB must be in line with the capacity of the charging cable (7.4 kW). In case the amperage rating of the charging cable is different than the amperage rating of the (MCB), the installer/user must change the station settings in the mobile app and/or web platform for station management as provided by the operator or service provider for this product.
This is a global product, and local wiring regulations & safety precautions within the country Of installation should be adhered to at all times.
The CITA Smart 7 will require Wi-Fi communications to unlock all smart features of the charger. Before installation, it is advisable to ensure a suitable Wi-Fi signal is available at your chosen point Of installation
Tools Needed For The Installation
Preparing for Installation
Use the supplied template to drill three fixing holes in the wall for the supplied screws
Fix both top screws to allow you to hang the charger
Once the charger is hanging from the top screws fix the charger firmly against the wall by screwing from internally the bottom screw.
Power supply cable installation from the rear or bottom of the charger
The charger should be mounted at least 1.3m from ground level
Note :
Cabling should be prepared to be inserted from the back or from the bottom of the EV Charger. Recommended to install the input power cable inside conduit. The charger should be mounted at least 1.3m from ground level.
*How To Register a CITA CONNECT APP with the CITA EV CHARGER - Click here
*How To Register a CITA EV Charger to a Monta OCPP backend using the EVSE Mesh APP - Click here