CITA Smart 7's Power balancer for single pile-CT clamp installation instruction
Power balancer for single pile-CT clamp installation instruction(AC7000-BE-34)
CT loop:
First step: Make the plug stand like this and take off the two screws, then input the two CT wires(red one is the n the left, white one is on the right), after that, take on two screws(make sure the wires can't be pulled off)
Second step: Find the two green receptions on the PCBA board which near the top left corner, and then insert the plug(take care of the directions, otherwise the plug can't be insert).
Third step: Clip the CT clamp over the live feed between the electricity meter and the consumer unit ensuring the arrow is pointing in the direction of the flow of energy.
How to Extend the CT clamp wire, so it reaches the EV Charger Installed Location?
The standard cable that is coming with the CITA CT Clamp is a 2-core 24AWG shielded twisted cable.
You can use a 24AWG specs cable to extend it. If the distance is very long from the DB and the charger point
it is recommended to use a copper cable of 95% or above to maintain the strength of the connectivity. Alternatively, you can also use CAT6 + Power cable if you want to make use of the available cable.
Still, Stuck?
If you are still having trouble following our guide, then please get in touch by either starting a live chat with our team, submitting a ticket Click here, or giving us a call at 0800 368 6362 / WhatsApp link +448003686362
We'll be happy to assist you!